South Korea is accelerating a major AI infrastructure project in Ulsan. During a November 21, 2026 site visit, President Lee Jae Myung urged faster development of the data centre being built by SK Group with Amazon Web Services.
The project is expected to involve about 7 trillion won (roughly US$5.2 billion) in spending through 2029. Operations are scheduled to begin in the second half of 2027, while the initial 103-megawatt capacity is planned by 2029. Larger expansion remains a future ambition, not completed capacity.
Why it matters: AI data centres drive demand for semiconductors, electricity and skilled construction workers. Lee said the Ulsan project could also bring technology investment beyond the Seoul region, while highlighting workforce and power-supply challenges.
Sources: Reuters, November 21, 2026; Yonhap News Agency, November 21, 2026.